Construction of a 35/11 kV substation at the 15th quarry of the Rogun Hydropower Plant.

Project Description

On September 8, 2017, CJSC TADES and Salini Impregilo S.p.A. signed contract No. 8400004804 in the Republic of Tajikistan for the construction of a 35/11 substation on the site of the 15th quarry of the Rogun Hydropower Plant.

The contract envisaged the construction of a 35/11 substation, including supplies of electrical equipment and materials, installation of steel intermediate individual poles in compliance with the requirements set by the applicable project specifications, rules and regulations.

The combined cost of the project is 5,820,400.43 somoni.

The 35\11 kV substation was commissioned on March 1, 2018, ahead of schedule.